Module schematic and BOM finalized

Hi there, and welcome to the monthly UHK status update!

TL;DR: The schematics and BOMs of the module PCBs and FPCs (Flexible Printed Circuits) have been finalized. Every part has been ordered for the modules.

Our contractor keeps making progress with the key cluster mold. This is how it looks:

As for the right-side modules, András has been refining their mechanical design, and I’ve been tweaking their PCBs accordingly. These are some of the boards I’ve redesigned recently:

I consider the schematics and BOMs of each PCB and FPC to be fully finalized. AndrĂĄs and I will meet over the next week and check how well the new 3D printed module cases fit with the new PCBs. Chances are high that everything will fit well, at which point the machining of the right-side module molds will begin.

I recently visited our EMC tester, TÜV, and we put the modules into the test chamber. The modules did not affect the measurements, which is exactly what I expected based on their small power consumption and small size. Given these results, the modules should pass the EMC tests with flying colors.

We’ve ordered every part of the modules from our suppliers. No parts shortages or delays are expected.

These days are unusually eventful due to the modules, hence this fabulously late monthly update. I’ll do my best to keep you up to date in a timely manner going forward, but I’ll keep prioritizing module development and production over the monthly updates for everyone’s sake.

Your tweets

You guys keep sending your awesome tweets, and we're always eager to read and feature them! If you got your UHK, please share your love!

We’ll be keeping you updated on all things UHK, and are looking forward to talking to you on 2020-06-16.

The key cluster molds are being made

Hi there, and welcome to the monthly UHK status update!

TL;DR: Key cluster mold manufacturing is well underway. We’re getting close to the final design of the right side module molds, too.

Since our last monthly update, the design of the key cluster molds has been finalized, and now they’re under production. It’s always quite an experience to witness hunks of steel taking shape.

In the meantime, AndrĂĄs and our contractor have been working hard to finalize the design of the right-side modules. As soon as this design gets finalized, our contractor will start to get these molds machined.

We’ve also ordered various parts, such as the optical sensor of the trackball, the mini trackball of the key cluster, and the FFC cables. This is quite an intense process for everyone involved, and we’re doing our best to hit our July ETA.

Feel free to change your shipping address any time.

Your tweets

You guys keep sending your awesome tweets, and we're always eager to read and feature them! If you got your UHK, please share your love!

We’ll be keeping you updated on all things UHK, and are looking forward to talking to you on 2020-05-11.

Module ETA announcement

Hi there, and welcome to the monthly UHK status update!

TL;DR: We expect to start shipping the modules in July, and we’re making rapid progress.

As mentioned in our previous monthly update, there are a number of tasks to be done to mass produce the modules, but the most time consuming of all is the creation of their molds. The good news is that our mold making supplier just provided us an ETA: June 2020. This means that we should be able to begin shipping orders in July, likely completing all orders in August.

Our supplier is almost ready with the design of the key cluster module mold:

AndrĂĄs has been working a lot on the 3D models of the modules recently, and all the modules should be finalized soon.

In the meantime, I’ve been busy optimizing the PCBs of the modules for manufacturing. It’s not rocket science, but there are a ton of details involved, and small tweaks can go a long way.

We’ve also started the procurement of the parts for the modules. Most of them are not very urgent, but there are exceptions like the optical sensor of the trackball module which can take up to 14 weeks to arrive. Luckily, we’re just in time to hit our ETA.

We’re knee deep into getting the modules manufactured, everything is going well, and we’ll be keeping you updated on a monthly basis as usual. You can change your shipping address any time.

UHK ninja belt

Special shootout goes to Hubert Łępicki who amused us with his UHK ninja belt (for the lack of a better term).

Hubert wouldn’t be a true ninja without demonstrating his belt in action. Check out the following video.

3rd party keycap sets

Some of you are on a never ending journey of pimping up your UHKs, and we’re excited to see your creations!

Further tweets

You guys keep sending your awesome tweets, and we're always eager to read and feature them! If you got your UHK, please share your love!

We’ll be keeping you updated on all things UHK, and are looking forward to talking to you on 2020-04-10.

Catching up with pre-orders

TL;DR: We’ve been making rapid progress with manufacturing. We’ve shipped six mini batches since our last monthly update, two additional mini batches are assembled and we will ship them next week. Afterwards, only three mini batches remain to be shipped, and we’ll be caught up.

Hi there, and welcome to our monthly status update! Ready for warp? Let’s punch it!

Manufacturing progress

Since our last monthly update, we’ve shipped mini batches 59, 60, 61, 62, 63, and 64, which is decent, but not as many as we had expected.

Mini batches 65 and 66 (the latter is not displayed on the delivery status page yet) are already assembled, but we’re waiting for palm rests. Our palm rest supplier is behind schedule, and is expected to ship enough palm rests next week to complete these mini batches. (We ship individual packages as quickly as we can, so no need to email about this, folks.)

Afterwards, we’ll only have to assemble about three mini batches. Should the Keyboard Gods show their support, we’ll catch up then.

That is, excluding orders which contain non-black cases. Those may take a bit more time. Which brings us to the...

Non-black case shortage

Due to a temporary shortage of non-black cases including non-black UHKs and non-black extra UHK cases, orders including such items are delayed until non-black cases roll into our factory. We emailed the affected customers, and offered them the option to switch to black cases to expedite shipping. So the opportunity is there. If you want to switch to black cases, just let us know along with your order id.

This shortage is expected to be resolved in about a month, and we don’t expect that a similar shortage will happen again. We ordered literally tons of colored plastic pellets, so we may not run out for years.

Module progress

András has refined the mechanical design of the key cluster module and ordered a 3D printed version of it which has yet to arrive. Then we’ll evaluate the robustness of the new design. Based on the CAD models, the design looks good. We shall see soon.

The mechanical design of the right-sided modules is being finalized, too. Some details are still unclear, but András made major progress recently, and we’ll get them 3D printed, too. The bottom part of these modules look very similar, and we want to have a shared bottom part for them in order to minimize tooling costs and increase reliability.

The design of the modules is rapidly shaping up, and I’ll have to develop the key cluster firmware soon.

Your feedback

Twitter was noisy, which has become usual when we ship a decent number of orders. Thanks everyone for sharing your nice tweets, and please keep them coming!

We’ll be keeping you updated on all things UHK, and we’re looking forward to talking to you on 2019-05-16.

Coming up to on-demand manufacturing

TL;DR: We’ve been making steady progress with manufacturing, and we’re about to switch into high gear. We expect to deliver every non-module pre-order by the end of March or the beginning of April. Afterwards, we’ll transition to on-demand manufacturing.

Hi there, and welcome to our monthly status update! Let’s get right to it!

Manufacturing progress

On February 27, we finally received the product boxes which were necessary to resume production, and we’ve shipped mini batches 55, 56, 57, and 58 since then.

Production has been mostly uninterrupted, except for a small shortage of foam parts that reside in the product boxes and protect your UHKs extremely well from any damage on the way. Luckily, we received plenty of foam parts today.

With the above issues out of the way, we expect to deliver every non-module pre-order by the end of March or the beginning of April, at which point we’ll transition to on-demand manufacturing.

On-demand manufacturing means that we’ll assemble orders as they come in. This translates to about a 0 to 5 working day delay from order to shipping depending on the actual demand.

Our current focus

Right now, our primary focus is to deliver every non-module pre-order, and streamline our operation. András is busy with the former, and I’m busy with the latter.

Improving our backend systems will allow us to devote the smallest amount of time possible to operational issues, and focus on R&D in general, and specifically the modules. So even though it’s not directly related to development, it will accelerate development, which is a prospect I’m really excited about.

Your feedback

Jez Cope, an awesome backer of ours has written a short review about his UHK, and so has Melinda Wyers on her blog. Thanks so much, Jez and Melinda!

The Twitterverse was eventful as usual featuring the following tweets:

We’ll be keeping you updated on all things UHK, and we’re looking forward to talking to you on 2019-04-18.

Shipping is about to resume

TL;DR: Delivery temporarily stopped due to the shortage of packaging material which should resume around February 20. We expect to ship every non-module preorder by the end of March. Regarding the ETA of your order, please check out the delivery status page, including its FAQ section.

Hi there, and welcome to our monthly status update! Let’s get right to it!

Manufacturing progress

Since our previous monthly update, we’ve built plenty of UHKs, but we couldn’t ship most of them due to a temporary shortage of packaging boxes.

It’s taken more time for the printing factory to get up to speed after new year, and they expect to deliver the packaging boxes to us on February 20. We’ll make quick progress once the boxes arrive, and expect to deliver every non-module preorder by the end of March.

We didn’t simply ask for another batch of packaging material to be honest. We redesigned the boxes because they weren’t sufficiently robust. The new boxes are not only fancy, but more robust (and more expensive).

I added a news section to the top of the delivery status page which you’re welcome to check any time. This way, you can keep informed about delivery status the easiest way possible.

DeveloperWeek cancelled

In our previous monthly update, we told you that the we’ll exhibit at DeveloperWeek in the Bay Area on February 21-22. Unfortunately, we won’t be able to make it.

The reason is that our marketing contractor was fired, because I found his work ethics to be poor. Without him, we can’t staff our booth, so I ended up cancelling the event.

With the event cancelled, we won’t be able to give away the free passes offered in our previous monthly update. I’m sorry about this, but now that we have cancelled the event, we can’t do anything. I’ll email all of you who asked for free passes shortly after publishing this update.

As far as the project is considered, I think not attending to DeveloperWeek is actually a good thing. We should fully focus on the delivery of preorders at this point. We’ll have plenty of time to do expos later.

Module progress

Robi has implemented the kboot bootloader protocol natively in Agent. Previously, Agent used the external blhost command line utility which was unreliable. This will make firmware updates more reliable which is very important because the modules will require a new firmware version flashed to your UHKs. We have yet to release a new Agent version that contains this improvement.

In the meantime, András advanced the mechanical design of the key cluster module, so it’s closer to the final design to be mass produced.

As stated in earlier updates, we can’t fully focus on the modules yet. Only after shipping every non-module preorder and transitioning to on-demand manufacturing will be able to make heavier progress regarding the modules.

Your feedback

Mikko Ahlroth wrote a very nice UHK review on his blog. I love reviews like his which go into details and capture many facets of the UHK.

In the meantime, Brett Terpstra has been exploring the wonderful world of custom keycap sets. He pimped up his UHK, and wrote a blog post titled The addictive hobby of customizing mechanical keyboards.

We’ll be keeping you updated on all things UHK, and we’re looking forward to talking to you on 2019-03-14.

Churning out UHK webshop preorders

Hi there, and welcome to our monthly status update! Let’s get right to it!

Manufacturing progress

Since our most recent monthly update, we have shipped mini batch 49, 50, 51, 52, 53, 54, and 55. As stated in our previous update, we had already shipped every Crowd Supply non-module pre-order, so all of the above orders were made in our own webshop which is a huge step forward.

We knew that transitioning from Crowd Supply orders to UHK webshop orders wouldn’t be easy, and in reality, it’s been way harder than anticipated. Compared to the fulfillment of Crowd Supply orders, the big change is that we don’t just ship to the EU anymore (we used to ship to non-EU countries via Crowd Supply), but worldwide ourselves, and we have to generate invoices upon shipping.

We learned a lot. For example, we learned that DHL, UPS, and FedEx are unwilling to ship to Russian individuals, but fortunately EMS is willing to take the job. We learned that the City field is not mandatory for Singapore which makes the DHL API unhappy. We learned that ZIP codes are not mandatory in Vietnam which made our invoicing system not create invoices. We learned that we have to validate order data upon checkout to avoid contacting some customers when trying to create waybills.

The above is a short glimpse of the issues we’ve been encountering. I’ve been tweaking our fulfillment system since our previous update, even during holidays, and András has been taking more than his fair share of these issues. We have now dealt with enough international packages that I can finally see the matrix, and I know what needs to be done to streamline our international fulfillment operation. When done properly, and it will be done properly, it’ll end up being a highly streamlined, and low overhead operation, but until that point, it kind of feels like we’re walking in mud.

Estimated delivery dates

TL;DR: If you order now, your UHK order is expected to be delivered by the end of February (barring modules, of course).

Right now, we’re held back by a temporary shortage of various components, including product boxes and plastic cases. We could foresee this shortage, and did our best to mitigate it, but companies were closed during holidays which slowed our progress.

If everything goes according our plans, this shortage will be resolved in two weeks, at which point production will get back to normal. We’re doing our best to deliver every one of your orders as soon as possible.

Module progress

We’ve had a get-together with our injection molding supplier and his mold designer specialist to finalize the mechanical design of the modules and optimize them for mass production.

Each module has its own set of challenges. Some are complicated from an electronics standpoint, others from a mechanical standpoint, and there’s also a significant difference in the firmware complexity of the individual modules.

We agreed that we will start with the key cluster module. The main reason is that its shape completely differs from every other module, so no parts of its mold can be reused for other modules. It’s also the most complicated module mechanically.

We had a fruitful discussion, and now we have a much better idea how to optimize the design of the key cluster module for mass production. The most challenging aspect of the key cluster module is its tiny trackball, and the compact design of the module in general, but all in all, it’s doable.

Please note that the aforementioned mud regarding international fulfillment is clearly not helping us accomplish heavy R&D on the modules, so right now we’re primarily focused on streamlining our fulfillment operation and transitioning to on-demand manufacturing. Once that’s done, the modules will get our full attention.

DeveloperWeek

We’ll exhibit at DeveloperWeek in the Bay Area on February 21-22, and you’re welcome to visit us! We happen to have 3 x EXPO PLUS passes ($795 value each) and 25 OPEN passes ($295 value each) to give away. Speakers at the DevWeek include:

  • Cal Henderson, Slack CTO and Co-Founder
  • Renaud Visage, Eventbrite Technical Co-Founder
  • Chet Haase, Google Lead, Android Toolkit

And many more… Check out the full schedule!

Want to get one of these passes? Please retweet this tweet. We will draw the winners on January 29th.

UHK reviews

If you’re into keyboards, the name of Xah Lee probably sounds familiar. He’s a hardcore keyboard geek who’s seen it all, and he recently reviewed the UHK.

According to his verdict:

  • “This is one of the best ergonomic keyboard on the market. I'd say, among top 3.”
  • “Among compact keyboards, this one is the best, period.”
  • “The programing capabilities of this keyboard is the best out there. The software, is also best on the market, bar none”
  • “The keyboard is highest quality built.”

The UHK was also reviewed by Frank MĂźller of Euronics. According to the article, Frank has a high opinion about the UHK, especially its configurability.

Your feedback

We’ll be keeping you updated on all things UHK, and we’re looking forward to talking to you on 2019-02-14.

Lunar UHKs, Unicorns, and the Freeze bug

Hi there, and welcome to our monthly status update!

TL;DR: Please update to the latest UHK firmware for macro support, and to help us fix the freeze bug that plagues recent firmware versions. Agent now visualizes secondary roles. We’ve churned out 6 mini batches since our last update. The development of the modules is going slowly while delivering the pre-orders, but we’ll switch to high-gear afterwards.

Update to the latest firmware!

If you’re reading this and already have your UHK, please flash the latest 8.4.5 firmware by selecting the .tar.bz2 file from the "Choose firmware and flash it" option in Agent > Firmware. This will result in many goodies over the factory-flashed 8.2.5 firmware, including macro support and numerous bug fixes.

The only gotcha is the freeze bug. Recent firmware versions cause occasional freezes on some UHKs. This is a longstanding bug, and the only reason we haven’t yet fixed it is because we can’t reproduce it. That’s why we need your help! The more people who use the most recent firmware, the easier we can fix the freeze bug based on your feedback.

If your UHK freezes, please be sure to report it according to the freeze bug issue. No worries, you can always downgrade to 8.2.5 to regain stability.

Fancy UHKs

If you’re a regular reader of our monthly updates then Max is no stranger to you, as he’s on a never ending quest to pimp his UHK. This time, he used the Godspeed Cockpit keycap set to customize his UHK and in his true style, he shared the gory details on Reddit.

In the same spirit, Richard was also busy, and ended up creating the most unicornish UHK with extra rainbow flavour!

Secondary role visualization in Agent

Dual-role keys are powerful. When tapping them they trigger their primary role. While holding them and pressing other keys, the secondary role kicks in. The UHK has always supported dual-role keys, but Agent hadn’t visualized them. Thankfully, this has just changed with Agent version 1.2.9.

Now Agent can render quite complex scenarios, such as a scancode featuring modifiers and a secondary role. This makes the rendering engine of Agent complete, so you can take a look at any layer and know exactly what each key does based on its visual representation.

As an added bonus, we’ve made modifiers show up according to your OS, so for example, Super is Command on OSX and it’s the Windows key on Windows.

Production progress

The 6 mini batches we have produced over the last month have not constituted our fastest pace, but they’re in line with our recent progress. Manufacturing progress occasionally suffers a bit due to a number of factors. For example, our palm rest supplier was on vacation recently, and had to catch up with production. Such cases only cause temporary hiccups, and they can occasionally affect the sizes of mini batches positively or negatively, but we always manage them quite well.

In the meantime, we’ve already pre-ordered the parts of the second large batch of UHKs. The first large batch contained 2,000 UHKs, and the second large batch contains 1,000 UHKs. We’re not VC-funded and fully rely on your support, so being able to pre-order the parts of a large batch is a big achievement for us. This means that production will be uninterrupted in the future, even after delivering the pre-orders. A sincere thank you to every one of our backers for making this huge milestone possible!

Development progress

As you can see, we keep pushing Agent and the firmware, but it’s quite a challenge to do heavy R&D these days because production and related tasks are so demanding.

Customer support is time consuming, as well as developing and fine-tuning backend systems. These tasks are not visible from the outside, but they’re absolutely necessary to keep things going.

Transitioning to our own webshop did end up heavily affecting our backend systems, including the integration and implementation of the webshop, factory automation, order fulfillment, and invoicing systems. Pre-ordering the parts of the second large batch also called for a procurement system which is up and running, but it has taken quite some time to set up.

Due to the above, we could only make a little progress with the modules. András has further refined their mechanical design, and will hand them off to a mold designer to finalize their mechanical features. I figured out how to optimally panelize their PCBs and factory-flash their firmware the most efficient way. We’re mindful about the modules, and will switch to high-gear once the delivery of the pre-orders is over.

Thank you for reading this update! We’ll be keeping you updated on all things UHK, and we’re looking forward to talking with you on 2018-10-12.

Webshop migration and manufacturing progress

Effective immediately, the Crowd Supply UHK pre-order page is closed. You can place orders in our own webshop from now on. Please read on for the details.

Hi there, and welcome to our monthly status update!

TL;DR: We’ve opened our own webshop! We’ve churned out 7 mini batches since our last update, which is the fastest we’ve ever produced. A ton of firmware progress has been made, but we need testers to fix a very hard to reproduce bug. We’ve received a lot of nice feedback from you, including a review.

Let’s start with the webshop migration, which is admittedly quite boring, but important.

Webshop migration

If you don’t plan to purchase more items from us, feel free to skip to the next section.

Crowd Supply has served us well. We launched a successful campaign, and they have been taking pre-orders up until this point, but now it’s time for us to take our own orders.

We have always wanted to run our webshop, because it allows us to provide the best possible customer experience. But setting up a decent shop is easier said than done. We’ve been very busy with bringing the UHK to market, so it’s taken quite some time for us to make our shop happen. Luckily, our efforts have come to fruition, and now our webshop is up and running.

At the same time, we’ve closed our Crowd Supply shop, so going forward, you can only order from our webshop. In the spirit of transparency, we’ll share everything you ever need to know about our shop. Please read on.

Delivery status

The delivery status page that contains the order ids of Crowd Supply orders will also contain the order ids of our webshop. I’m working on integrating this page with our webshop, which may take a week or two.

Please note that our webshop has just recently started, so its order ids are in the hundreds vs the order ids of Crowd Supply which are in the tens of thousands. To make this distinction clear, the order ids of our webshop will be prefixed by “#”.

Our first-come, first-served delivery policy will not be affected by this transition regardless of which webshop you ordered from.

New shop features

Our new shop offers quite a few advantages:

First, you can choose three separate currencies: USD, EUR, and HUF. The prices of the relevant currency will be shown. This results in no conversion fees if you happen to use one of these currencies.

Second, you can pay not only with your credit card, but also with PayPal. Over time, we plan to introduce further payment methods.

Third, there are separate product pages, and the pages of configurable products contain a visual product configurator. You can see a preview image that shows the exact product that you’ll receive.

Fourth, our webshop generates proper invoices. This is mainly beneficial for company purchases.

Shipping

When it comes to shipping, the first thing to highlight is delivery times. So far, we’ve directly delivered from Hungary to the EU, which is great, because it only takes about a day or two for the packages to arrive. Delivering outside of the EU however has been less than ideal because we previously sent those packages via Crowd Supply (Portland, USA). It takes a couple of days for them to receive the packages, then it can take a week or two until they forward them. It’s especially painful for countries outside the EU and USA because it can take as much as a month to receive the package starting from the day we shipped it!

This had to change, so going forward, when you order from our webshop, we’ll send the package directly from our factory in Hungary to you which shouldn’t take more than a couple of days regardless of your country.

When it comes to shipping costs, Crowd Supply has a very simple pricing structure: shipping free to the US, and $24 to everywhere else. This clearly doesn’t reflect the actual cost of shipping, because it does cost money to ship goods to the US, and the shipment of smallish packages is often cheaper than $24 outside the US.

Our philosophy is that we don’t want to earn or loose on shipping. We will simply pass the shipping cost to our customers. We use DHL, and we’ve made quite a good deal with them. The current shipping costs are based on the weight of the package, and your destination. You can see the actual shipping cost on the cart page of our webshop. For example, it currently costs $15.14 to ship a UHK to Switzerland, $19.03 to the USA, and $29.93 to Japan. For some of you, it’ll be cheaper, but for those of you who will pay more (mostly because of your location), it’ll be a lot faster!

Multiple / aggregated orders

If you have made orders on Crowd Supply, feel free to make further orders in our shop. In this case, please specify the same email address as on Crowd Supply. This way, we’ll be able to aggregate your Crowd Supply and non Crowd Supply orders, and ship them once if you happen to be from the EU. The reason order aggregation only works for EU customers is because we need to ship non-EU orders separately via Crowd Supply.

If you make multiple orders in our own webshop then the shipping cost will always added for every single order. Given that we’ll ship your orders together, the actual shipping cost will be lower. The way we’ll make this fair is that upon delivery, we’ll take the sum of the shipping costs you paid, subtract the actual shipping cost of the package that contains all your orders, then refund the difference to you.

EU VAT

Please note that this section only applies to EU citizens and companies. Feel free to skip to the next section if it’s not relevant to you.

According to tax laws, VAT must be paid when purchasing goods within the EU. The VAT rate of the origin country applies, which is 27% in Hungary. This means that given a $100 product, the final price will be $127 with VAT included, unless you’re a company.

Some of you may have noticed that this seemingly wasn’t the case so far. Our items did cost the same worldwide, the EU included. This was possible because we actually reduced the net prices of items for EU customers to offset the VAT, so we were willing to take a heavy hit on our margin for making our pricing more competitive for EU customers.

Starting from now, we won’t offset our prices anymore, and VAT will be applied. If you don’t want to pay VAT in the EU, your only choice is to purchase the goods as a company. In this case, you’ll have to provide your company’s valid EU VAT number on the checkout page, and then VAT will not be added, and it will not be featured on the invoice.

Discounts

The 10% discounts are still in effect in our new shop. We’ll remove the discounts of non-module items once all these pre-orders shipped. Afterwards, we’ll remove the discounts of module items once all these pre-orders are shipped.

Who to contact?

Regarding the items that you purchased on Crowd Supply, contact them at [email protected]. Regarding the items that you purchased in our webshop, contact us at [email protected].

Manufacturing progress

Since our last update, we’ve sent out mini batches 16, 17, 18, 19, 20, 21, and 22, which is, yet again, the highest volume batch we’ve produced so far. The production throughput of the last month is 84% of what we planned, so we’re quite close, and working to increase it further.

We’ve just looked into the stats and realized that we’ve already shipped most of the pre-orders. We shall proceed further.

Firmware progress

Eric, our intern has been hard at work. He’s implemented the macro engine, vastly improved the debouncing algorithm, fixed various bugs related to secondary role handling, and more. What a huge step forward! All of these changes are part of the latest pre-released 8.4.4 firmware.

And still, the latest stable firmware release that is recommended and which is flashed in our factory is 8.2.5 which is 152 commits behind the tip of the master branch! This drives me crazy. And why’s that? Because of the freeze bug.

This bloody bug makes the UHK freeze once in a while. The trick is that it’s extremely hard to reproduce. On my UHK, it hits less than once in a month. On some others, it’s considerably more frequent, and occurs on a daily basis.

I could go on and on about this bug, but the bottom line is that if you want to use the new features and improvements while still having stability, then please flash the latest pre-release firmware, subscribe to the freeze bug GitHub issue, and let us know your findings. We’ll release new firmware versions shortly, and will ask you to test them for stability and share your feedback. The faster and more detailed feedback you provide, the quicker we can fix this bug. And you can always downgrade to 8.2.5 if the freeze bug hits too often before we fix it.

Your feedback

Kyle Holgate, an awesome backers of ours wrote a review about his UHK. It’s a very nice write up, and you’re welcome to read it.

Meanwhile, Max, in this true style, was busy with pimping his UHK yet another time, created the most nuclear UHK to this day, and made quite some noise on reddit. Please keep up the great work, Max!

You guys keep sending us your nice mods and feedback all over the interwebs. We’re honored and delighted!

Thank you for reading this update! We’ll be keeping you updated on all things UHK, and we’re looking forward to talking with you on 2018-09-13.

Production is up and running

Important: Please make sure that your shipping address is up to date! You can change it on your Crowd Supply account page. Please also check out the delivery status page.

Hi there, and welcome to our monthly status update!

TL;DR: Our factory is up and running! According to the aforementioned delivery page, we’ve already sent out the first mini batch, so some of you should get your orders within days. Given our most recent production data, we’ll be able to deliver batch 1 of 2,000 UHKs and related accessories by the end of July. Many of you will get your orders much faster depending on your place in the queue. Everything’s looking great, and we’ll be transitioning to the modules soon.

Some UHKs of mini batch 1:

Manufacturing progress

Launching mass production wasn’t exactly a smooth ride, which wasn’t really surprising after all. Given our past experience, some things inevitably go wrong despite our best efforts.

We observed that some LED segments displayed gibberish - that is, unidentifiable characters. It was quite a challenge to figure out the root cause of this, but András succeeded. Apparently, the space is very tight around the FFC cable and when the case is on, it bends the cable and some pins don’t connect. The solution? We just have to bend the FFC cables in an M shape prior to assembly.

We also noticed that some pins of some through-hole components, most notably the keyswitches and the 4P4C connectors, weren’t soldered in on some boards. We talked to our PCBA supplier who told us that their selective wave soldering machine had been misbehaving and got serviced recently. They will also use a 3-dimensional automated optical inspection machine from this point forward which should greatly reduce defects. The problematic boards will be reworked.

Then we were faced with a couple of bent plates. We have yet to figure out how these plates could possibly bend, but for the time being, we’ll do heavier QA until the cause is revealed and eliminated.

And lastly, a critical piece of launching manufacturing is our custom developed order fulfillment and manufacturing execution system that I’ve been working full steam on in the last couple months. It felt like building a runway while the plane takes off, but the runway has been built just in time, and now the plane is in the air.

Given the above issues, we started up slowly. According to our most recent measurements based on actual production data, we will be able to ship about two mini batches per week, which equals about 120 UHKs and related accessories. Given this pace, we’ll be able to deliver batch 1 by the end of July, so this is our current delivery target. Of course, many of you will get your orders way faster depending on your place in the queue.

Agent and firmware progress

Starting with the latest firmware, it’s now possible to wake up the host computer with a touch of a key. The LED display also gets disabled when the host sleeps to save power. See the firmware changelog and releases.

Agent got a shiny new desktop icon, it now displays the firmware versions running on the halves of your UHK, and can recover UHKs with broken configurations. See the Agent changelog and releases.

Going forward

The next big milestone is clear: the modules. The modules clearly differentiate the UHK from every other keyboard in the market, and make it the first and so far only modular keyboard ever created.

Personally, I can’t wait to control the pointer in various ways in a finer grained manner without leaving the home row, and I know that a lot of you share our enthusiasm. I’m sure the journey will be just as exciting as getting there, and as always, we’ll make you part of the journey via these updates.

Thank you for reading this update! The next one will be published on 2018-05-17. In the meantime, feel free to keep checking the delivery status page of your much awaited UHKs.